BuildPlatinum Pty Limited v Micaleff

Table of Contents

Case Overview

Case Name: BuildPlatinum Pty Limited v Micaleff

Case Number: [2021] NSWCATAP 129

Date of Decision: 12 May 2021

Tribunal/Court Name: Civil and Administrative Tribunal, New South Wales

This case revolved around a building dispute regarding defective roof sheeting in a residential construction project. The homeowners, Carol and Laurence Micallef, alleged that the builder, BuildPlatinum Pty Limited, breached statutory warranties under Section 18B of the Home Building Act 1989 (NSW), ultimately leading to an appeal regarding the application of Section 18F of the Act.

Key Parties

Homeowner Details: Carol Micallef and Laurence Micallef

Builder Details: BuildPlatinum Pty Limited

No additional parties were involved in this case.

Project Details

Type of Residential Work: Residential building construction

Original Contract Price: $450,000

Final Project Cost: $797,540

Contract Type: Fixed price contract

Nature of the Dispute

The primary issues raised by the homeowners included:

  • Allegations of defective roof sheeting installation
  • Breach of statutory warranties under Section 18B of the Home Building Act

The builder responded with a claim for unpaid variations and asserted that any defects were due to the homeowners’ instructions, including a specific mention of Section 18F as part of their defence.

Section 18F Defence Details

The builder raised a Section 18F defence, which stated that the deficiencies in the construction arose from:

  • Instructions contrary to advice: The builder contended that they had received instructions from the homeowners that contradicted their expert recommendations.
  • Reliance on relevant professional: The builder claimed to have relied on a qualified professional, whose advice they followed throughout the project.

Relevant Professional’s Role

Type of Professional Involved: Building consultant

Professional’s Qualifications: Mr. Zakos, an experienced building consultant who testified on roofing standards.

Independence Assessment: Mr. Zakos was independently retained by the homeowners and was not influenced by the builder.

Key Evidence Presented

Homeowner’s Evidence: The homeowners provided expert testimony regarding the defects found in the roof sheeting, particularly highlighting the use of inappropriate materials.

Builder’s Evidence: The builder presented their case but did not provide independent expert testimony to refute the claims made by the homeowners.

Expert Testimony: Mr. Zakos’ evidence was crucial in establishing that the roof sheeting installed was defective and non-compliant with safety standards.

Tribunal/Court’s Analysis

The Appeal Panel interpreted Section 18F as a critical measure concerning the builder’s obligation to demonstrate that deficiencies arose strictly from the instructions given or reliance on independent professionals. As the builder’s assertions about the professional involvement and instructions were not sufficiently substantiated with evidence, the tribunal could not validate the defence’s claims.

Decision and Outcome

The Appeal Panel ultimately rejected the Section 18F defence, stating:

  • The builder failed to demonstrate that the deficiencies were due to compliant instructions from the homeowners.
  • Key evidence from the expert witness supported the homeowners’ claim of defective installation.

As a result, the tribunal ordered that damages of $455,225.80 be awarded to the homeowners, reinforcing the importance of compliance with statutory warranties.

Financial Implications

The awarded damages included the cost to remedy the major defects, specifically related to the inappropriate roofing materials estimated at $233,144.75. Additionally, costs were awarded towards the homeowners’ legal expenses, further emphasising the financial ramifications for the builder due to their failure to adhere to warranty standards.

Lessons for Homeowners

This case serves as a reminder for homeowners regarding:

  • The significance of retaining independent experts for advice on construction projects.
  • The necessity for clear documentation of all communications and instructions throughout a build.
  • The importance of being aware of statutory warranties and the protections available under the Home Building Act 1989 (NSW).

Broader Implications

The outcome of this case may influence similar disputes by:

  • Reinforcing the requirement for strict adherence to building codes and compliance with Section 18B warranties.
  • Encouraging more stringent practices in considering professional advice during construction.
  • Spurring potential legislative reviews to ensure clarity in warranty terms and homeowners’ rights.

Take Warranty
Wisdom into Action

Use HBApp to apply legal insights 
to your home project

Need Expert Advice on Your Building Dispute?

While our case summaries provide valuable insights, every building dispute is unique.

Get personalised guidance from a qualified professional.

Begin Your Journey to a Dream Home Today

Ready to transform your home building experience? Sign up for a free trial and unlock the full potential of Home Building App. Discover how our comprehensive project management tools can simplify your build, ensuring your project remains on time, within budget, and of the highest quality.