Fisher v N. Phillips and M. Phillips t/as Arise Building Services

Table of Contents

Case Overview

Case Name: Fisher v N. Phillips and M. Phillips trading as Arise Building Services

Case Number: [2022] NSWCATCD 80

Date of Decision: 25 May 2022

Tribunal/Court Name: Civil and Administrative Tribunal of New South Wales

This case revolves around a dispute regarding alleged defective residential building work undertaken by the builder, resulting in claims for compensation from the homeowners. The homeowners, Craig and Theresa Fisher, sought damages for rectifying the defective building work, claiming breaches of statutory warranties under the Home Building Act 1989 (NSW).

Key Parties

Homeowners: Craig Fisher and Theresa Fisher, represented by D Neggo (Counsel) and Stacks Law Firm (Solicitor).

Builder: N. Phillips and M. Phillips trading as Arise Building Services, represented by Jane Button & Associates Pty Ltd (Solicitor).

Project Details

Type of Residential Work: Additions and alterations to a residential dwelling.

Original Contract Price: $137,500 (inclusive of GST).

Final Project Cost: $49,168.35 ordered as compensation.

Nature of the Dispute

The homeowners raised numerous issues regarding alleged defects resulting from the builder’s failure to adhere to statutory warranties under Section 18B of the Home Building Act. The main points of contention included:

  • Water ingress issues.
  • Damage to plasterboard ceilings and walls.

The builder countered these claims, arguing that the defects were due to design faults and maintained that they had built according to the provided plans and specifications.

Timeline of Events

Contract Signing Date: 02 November 2015

Actual Completion Date: Achieved practical completion around July 2016; Occupation Certificate issued on 01 June 2017.

The homeowners filed a claim with the Tribunal on 10 December 2020, indicating alleged defects within the statutory warranty periods.

Defects and Incomplete Work

The homeowners alleged multiple defects, primarily focusing on the following:

  • Water ingress through the roofing system and external windows.
  • Damage to internal plasterboard ceilings and walls due to the water ingress.

Expert opinions were presented, with the homeowners’ expert asserting significant structural concerns requiring remediation, while the builder’s expert minimised the necessity for extensive work.

Financial Impact

Amount Claimed by Homeowner: $49,168.35 for rectification of defects.

Counter-Claims by Builder: None filed.

Cost of Rectification: Expert estimations led to a total judgment amounting to $49,168.35, covering necessary repairs and remediation costs.

Tribunal’s Key Findings

The Tribunal determined that the builder had breached statutory warranties outlined in Section 18B of the Home Building Act. Key findings included:

  • The identification of major defects caused by ineffective waterproofing and inadequate workmanship.
  • Assessment of evidence, expert testimony, and the specifics of each alleged defect.

Outcome and Orders

The Tribunal ruled in favour of the homeowners, orders issued included:

  • Monetary award of $49,168.35 to the homeowners from the builder.
  • Order for the builder to pay the homeowners’ legal costs.

Reasons for Decision

The Tribunal relied on key legal principles concerning breaches of statutory warranties and outlined relevant sections of the Home Building Act. Emphasis was placed on the builder’s responsibilities to meet the expectations set by both the Act and the contract, even if performed in accordance with plans.

Lessons for Homeowners

This case reinforces the importance of understanding your rights under the Home Building Act, particularly:

  • Awareness of statutory warranties that protect homeowners.
  • The critical need for documentation and effective communication throughout the building process.

Implications for Similar Cases

As a result of this decision, several precedents were set, indicating a clear directive for builders to abide by statutory warranties. Homeowners facing similar disputes can draw confidence from this case, knowing the strength of their rights under the Home Building Act.

Next Steps

The Tribunal ordered the builder to compensate the homeowners with a strict compliance timeframe of 28 days to fulfil this obligation. Homeowners should remain vigilant regarding compliance requirements and should consider their options for legal recourse or appeal if similar issues arise in the future.

Navigate Building 
Disputes Confidently

Use HBApp to apply legal strategies and 
resolve claims effectively

Need Expert Advice on Your Building Dispute?

While our case summaries provide valuable insights, every building dispute is unique.

Get personalised guidance from a qualified professional.

Begin Your Journey to a Dream Home Today

Ready to transform your home building experience? Sign up for a free trial and unlock the full potential of Home Building App. Discover how our comprehensive project management tools can simplify your build, ensuring your project remains on time, within budget, and of the highest quality.