Hertslet v Doherty; Doherty v Hertslet

Table of Contents

Case Overview

The case of Hertslet v Doherty; Doherty v Hertslet (2016) was decided by the Civil and Administrative Tribunal of New South Wales on 23 February 2016. This case revolved around a dispute between homeowners and a contractor regarding the installation of a kitchen, with particular focus on allegations of defective work and compliance with Section 18B of the Home Building Act 1989 (NSW).

Project Details

The central issue involved a kitchen installation, where the contractor, Douglas Hertslet, claimed a fee of $12,829 for work completed, while the homeowners, Peter Doherty and Jane Swinhoe, sought $52,000 for rectification of alleged defects in the installation. Ultimately, the settlement reached was for the contractor to pay the homeowners $32,000 in three instalments, supported by the delivery of specific materials.

Parties Involved

The parties in this dispute comprised:

  • Homeowners: Peter Doherty and Jane Swinhoe
  • Contractor: Douglas Hertslet trading as Kitchen Excellence

Nature of the Dispute

The dispute emerged from claims made by both parties: the contractor sought payment for work purportedly completed, while the homeowners argued that the kitchen installation was defective. Specific warranties under Section 18B of the Home Building Act, which mandates that work must be carried out in a proper and workmanlike manner, were allegedly breached. Claims included:

  • Defective kitchen cabinetry and installation
  • Failure to accommodate the specified model of dishwasher

Claim Details

The homeowners, in response to perceived failures in the construction quality, claimed an estimated amount of $52,000 for the rectification of defects. The counter-claim from the builder for unpaid work amounted to $12,829 under the contract.

Key Findings

The tribunal found that the contractor had indeed breached the statutory warranty set out under Section 18B by failing to deliver a product that met the specified standards of workmanlike performance. The determination concluded that the defects were significant enough to warrant remedial action.

Outcome

The tribunal favoured the homeowners, allowing their appeal and setting aside the previous orders for costs. The tribunal ruled that:

  • No order for costs was warranted as both parties acted reasonably.
  • The claims were intertwined, indicating a compromise rather than a capitulation by either party.

Important Considerations

The case referenced critical legal principles surrounding the awarding of costs in situations where matters have settled. Notably, the tribunal’s decision emphasised the distinction between cost applications following a contested hearing versus those resulting from settlements.

Key Sections and Interpretation of the Home Building Act and Relevant Case Precedents

The tribunal’s interpretation of Section 18B was key to determining outcomes in the case. The ruling emphasised that:

  • Work must be performed in a proper and workmanlike manner, governed by statutory warranties.

Key Lessons for Homeowners Facing Building Disputes

This case underscores several important lessons for homeowners facing building disputes:

  • Document Everything: Keep thorough records of agreements, communications, and work performed.
  • Know Your Rights: Understand the statutory warranties provided under the Home Building Act.
  • Seek Legal Advice Early: Engage legal counsel at the onset of a dispute.
  • Consider Settlement Options Carefully: Analyse any offers made by the contractor.

Take Warranty
Wisdom into Action

Use HBApp to apply legal insights 
to your home project

Need Expert Advice on Your Building Dispute?

While our case summaries provide valuable insights, every building dispute is unique.

Get personalised guidance from a qualified professional.

Begin Your Journey to a Dream Home Today

Ready to transform your home building experience? Sign up for a free trial and unlock the full potential of Home Building App. Discover how our comprehensive project management tools can simplify your build, ensuring your project remains on time, within budget, and of the highest quality.