Impressive Builders Pty Ltd v Cleary

Table of Contents

Case Overview

Case Name: Impressive Builders Pty Ltd v Cleary

Case Number: [2021] NSWCATAP 331

Date of Decision: 26 October 2021

Tribunal/Court Name: Civil and Administrative Tribunal, New South Wales

Brief Description of the Dispute: This appeal concerned a dispute arising from renovation work undertaken by Impressive Builders Pty Ltd (the builder) for homeowners Glenn and Amanda Cleary. The case focused on the builder’s alleged defective and incomplete work, resulting in the homeowners seeking compensation.

Key Parties

  • Homeowner Details: Glenn Cleary and Amanda Cleary – Self-represented individuals.
  • Builder Details: Impressive Builders Pty Ltd, represented by Mr D Condon (Director of Appellant).

Project Details

  • Type of Residential Work: Renovation
  • Original Contract Price: Not specified
  • Final Project Cost: Not specified
  • Contract Type: Not specified

Nature of the Dispute

  • Main Issues Raised by the Homeowner: The homeowners alleged that the builder’s work was defective and incomplete, seeking compensation of $14,306.53.
  • Builder’s Response: The builder counterclaimed for $6,893.26, asserting the homeowners owed this amount for the final invoice despite claiming no liability for the alleged defects.
  • Relevance to Section 48MA: Section 48MA of the Home Building Act provides a framework for the tribunal to consider if rectification is the preferred outcome in cases of defective work.

Section 48MA Considerations

  • Whether Rectification Was Ordered: No rectification order was made; instead, the Tribunal ordered payment of compensation to the homeowners.
  • Reasons for the Rectification Decision: The Tribunal determined that the builder had ceased work and had no intention of returning, coupled with the extensive nature of the defects found by expert testimony.
  • Court’s Interpretation of Section 48MA: While rectification is considered the preferred outcome, the Tribunal examined the specific circumstances and deemed a monetary order more appropriate.

Rectification Details

  • Scope of Rectification Work Ordered: Not applicable due to the compensation decision.
  • Responsible Party for Rectification: Not applicable.
  • Estimated Cost and Timeframe for Rectification: Not specified since the Tribunal awarded financial compensation instead.

Parties’ Positions on Rectification

  • Homeowner’s Stance: The homeowners insisted on compensation for the defective works instead of rectification due to the builder’s failure to complete the project.
  • Builder’s Stance: The builder contended that it should not be held liable for the defects and highlighted issues with the homeowners, arguing for the right to finish the work.
  • Reasons for Any Opposition to Rectification: The deteriorated relationship between the parties and the builder’s lack of intention to complete the work influenced the decision against a rectification order.

Expert Evidence

  • Key Points from Expert Testimony: Expert Neil Wallace provided a comprehensive report outlining significant defects, including poor alignment and lack of due care in the renovation work.
  • Expert Recommendations on Rectification: Extensive rectification work was required, with costs estimated at $14,306.53, determining that the builder failed to adhere to acceptable standards.
  • Feasibility and Challenges of Rectification: Due to the relationship breakdown and builder’s non-compliance, rectification was deemed unfeasible, leading to a money order instead.

Outcome and Impact

  • Final Decision on Rectification: The Tribunal opted for a monetary compensation order rather than rectification due to the circumstances of the builder’s conduct.
  • Any Additional Compensation Ordered: The builder was ordered to pay $14,306.53 to the homeowners.
  • How the Case Was Resolved Through Rectification (if applicable): No rectification order was issued; the case concluded with a financial award to the homeowners.

Lessons for Homeowners

  • Key Takeaways from the Case: Homeowners should ensure they have clear contracts outlining the terms of work and maintain communication with builders regarding any issues.
  • Implications for Similar Disputes: This case illustrates the importance of documenting issues and expert advice in disputes with builders.
  • Advice for Homeowners in Similar Situations: Engage legal advice early, consider obtaining expert reports on works, and document all communications and agreements with builders.

Compliance and Enforcement

  • Measures to Ensure Compliance with the Rectification Order: Not applicable due to financial compensation.
  • Any Follow-Up Inspections Required: Not applicable.

Timeframes and Costs

  • Time Between Defect Identification and Rectification Order: Not applicable as no rectification was ordered.
  • Estimated vs. Actual Costs of Rectification: Not specified due to the nature of the order made.

Alternative Remedies

  • Any Alternatives to Rectification Considered: Rectification was the primary consideration, but given the circumstances, a monetary order was deemed more suitable.
  • Reasons for Choosing Rectification Over Alternatives: The builder’s failure to complete work and the deteriorated relationship negated the possibility of rectification.

Legal Implications

  • Any Novel Applications or Interpretations of Section 48MA: The case highlights the tribunal’s discretion under Section 48MA, acknowledging that while rectification is preferred, it is not mandatory.
  • Potential Precedent Set by This Case: It serves as guidance for future disputes, especially regarding the application of Section 48MA in similar residential building claims.

Navigate Building 
Disputes Confidently

Use HBApp to apply legal strategies and 
resolve claims effectively

Need Expert Advice on Your Building Dispute?

While our case summaries provide valuable insights, every building dispute is unique.

Get personalised guidance from a qualified professional.

Begin Your Journey to a Dream Home Today

Ready to transform your home building experience? Sign up for a free trial and unlock the full potential of Home Building App. Discover how our comprehensive project management tools can simplify your build, ensuring your project remains on time, within budget, and of the highest quality.