Case name: Payne v Keene

Case number: [2022] NSWCATAP 236

Date of decision: 18 July 2022

Tribunal/court name: Civil and Administrative Tribunal of New South Wales

Brief description of the dispute: This case revolves around a construction dispute where a builder, Aaron Payne, was ordered to remove and reinstate a deck he built for homeowners, Phillip and Leanne Keene, following allegations of non-compliance with installation guidelines and defective workmanship.

Key Parties

  • Homeowner details: Phillip Keene and Leanne Keene, homeowners who retained the builder for a deck installation at their property in Northwood.
  • Builder details: Aaron Payne, self-represented builder who undertook the construction of the deck.

Project Details

  • Type of residential work: Deck Construction
  • Original contract price: $8,866 (inclusive of GST)
  • Final project cost: $8,862.70 (amount invoiced)
  • Contract type: Not specified

Compliance with Section 92

  • Main issues related to Section 92: The case primarily dealt with issues surrounding defective building work and compliance with statutory warranties.
  • Specific subsections of Section 92 involved: While Section 92 is not directly referenced, the principles of compliance and defects fall under the broader obligations of the Home Building Act.
  • Builder’s compliance status: Found non-compliant due to inadequate workmanship.

Legal Arguments

  • Homeowner’s main claims: The homeowners claimed that the deck construction was defective, specifically regarding the inadequate step down and incorrect installation of Scyon sheeting, as outlined in the James Hardie Installation Guide.
  • Builder’s defenses: Aaron Payne argued that he had followed proper procedures, claiming homeowner interference and denial of access as contributing factors to the shortcomings alleged by the homeowners.
  • Key legal principles applied: This case examined the statutory warranties under Section 18B of the Home Building Act and the implications of implied terms regarding compliance with manufacturer installation guidelines.

Evidence and Expert Opinions

  • Types of evidence presented: Both parties presented expert reports detailing the alleged defects and compliance issues.
  • Expert testimonies: The tribunal relied on evidence from construction experts, who provided conflicting assessments of the work’s compliance with regulations.
  • Tribunal/court’s assessment of the evidence: The tribunal favored the homeowners’ expert’s assessment, leading to the ruling against the builder.

Tribunal/Court Decision

  • Finding on Section 18B breach: The tribunal found that the builder had breached his obligations by failing to comply with the James Hardie Installation Guide.
  • Orders: The builder was ordered to remove the existing deck and reinstate it correctly, estimated to cost $8,862.70.
  • Penalties imposed: No financial penalties were imposed, but strict compliance orders were issued.

Rectification Work

  • Details of original work: Aaron Payne constructed a front deck for the homeowners which was later deemed non-compliant and defective.
  • Rectification performed: The tribunal ordered the removal and correct reinstatement of the deck in alignment with the James Hardie Installation Guide.
  • Cost and coverage of rectification: The estimated cost was $8,862.70, as per the builder’s invoicing.

Financial Impact

  • On the homeowner: Homeowners were not required to pay the builder until compliance was secured, thereby temporarily alleviating financial burden.
  • On the builder: Aaron Payne faced significant financial implications due to the requirement to rectify the defective work at his expense.

Key Takeaways for Homeowners

  • Important lessons from the case: Homeowners should ensure that all aspects of construction comply with both contractual agreements and manufacturer guidelines.
  • Preventative measures: Engaging qualified experts for inspections and maintaining clear documentation throughout the construction process can safeguard homeowner rights.
  • Rights and responsibilities under Section 18B: Homeowners are entitled to statutory warranties that protect against defective workmanship.

Broader Implications

  • Impact on industry practices: The ruling reinforces the importance of adherence to installation guidelines and may lead to stricter industry oversight.
  • Potential regulatory changes: There may be calls for clearer regulations regarding compliance with manufacturer instructions in the Home Building Act.
  • Precedent set: This case underscores the significance of ensuring construction work meets regulatory standards and can serve as a reference for future disputes involving similar issues.

Navigate Building 
Disputes Confidently

Use HBApp to apply legal strategies and 
resolve claims effectively

Need Expert Advice on Your Building Dispute?

While our case summaries provide valuable insights, every building dispute is unique.

Get personalised guidance from a qualified professional.

Begin Your Journey to a Dream Home Today

Ready to transform your home building experience? Sign up for a free trial and unlock the full potential of Home Building App. Discover how our comprehensive project management tools can simplify your build, ensuring your project remains on time, within budget, and of the highest quality.