Samchris Pty Ltd v Keogh

Table of Contents

Case Overview

Case name: Samchris Pty Ltd v Keogh

Case number: [2024] NSWCATAP 125

Date of decision: 28 June 2024

Tribunal/court name: Civil and Administrative Tribunal of New South Wales

Brief description of the dispute: This case involves a home building dispute in New South Wales, where the homeowners, Steven and Jacqueline Keogh, claimed that the builder, Samchris Pty Ltd, caused water ingress into their master bedroom, resulting from defects in construction and a breach of statutory warranties under the Home Building Act 1989 (NSW).

Key Parties

Homeowner details:

The homeowners are Steven John Keogh and Jacqueline Mary Keogh, who own the property located in Baulkham Hills, New South Wales.

Builder details:

Samchris Pty Ltd is a company acting as the builder, represented by Lawandi Lawyers.

Any other relevant parties:

The respondents were also represented by counsel from Michael Atkinson & Associates.

Project Details

Type of residential work: Two-storey extension to the existing dwelling, which included a master bedroom and laundry area.

Original contract price: $431,778.00 (inclusive of GST).

Final project cost: Not specified.

Contract type: HIA NSW Residential Building Contract for Renovations and Additions.

Nature of the Dispute

Main issues raised by the homeowner: The homeowners claimed that the builder had breached statutory warranties concerning water ingress into the master bedroom and defective works.

Builder’s response and defences: The builder denied liability, asserting that design flaws and pre-existing issues not related to their work were responsible for the defects.

Specific mention of Section 18F defence (if applicable): The builder attempted to invoke a defence under Section 18F of the Home Building Act, claiming reliance on a professional’s instructions regarding the design.

Section 18F Defence Details

Type of Section 18F defence raised: The builder claimed reliance on instructions given by a design professional.

Key elements of the defence:

  • Instructions contrary to advice: Not applicable.
  • Reliance on relevant professional: The builder relied on a design from an engineer, Jake Fugar, concerning the stormwater management design.

Relevant Professional’s Role

Type of professional involved: Engineer.

Professional’s qualifications: Jake Fugar from SDA Structures, responsible for the design aspects.

Independence assessment: The Tribunal found that Fugar’s independence was questionable as he was perceived to act on the builder’s behalf rather than solely for the homeowners.

Key Evidence Presented

Homeowner’s evidence: The homeowners provided photographic and expert evidence illustrating persistent water ingress.

Builder’s evidence: The builder brought forward expert reports attempting to demonstrate pre-existing drainage issues.

Expert testimony: Expert testimony from Tony Dockrill indicated significant moisture issues attributed to construction failures concerning stormwater management.

Tribunal/Court’s Analysis

Interpretation of Section 18F: The Tribunal reviewed the legitimacy of the builder’s reliance on the professional’s advice and the implications of the design provided.

Assessment of the defence’s validity: The Tribunal concluded that the builder failed to establish that the design effectively absolved them from responsibility for the defects.

Consideration of professional’s independence (if relevant): The Tribunal highlighted the interconnected relationship between the builder and the engaged professional, impacting the defence’s credibility.

Decision and Outcome

Whether the Section 18F defence was accepted or rejected: The Section 18F defence was ultimately rejected due to insufficient evidence establishing that the builder could rely on the engineer’s instructions as an excuse for the defects.

Reasons for the decision: The Tribunal found that the builder had not fulfilled its obligations under the statutory warranties of the Home Building Act.

Impact on the overall case outcome: The decision favoured the homeowners, with the builder ordered to rectify defects and pay associated costs.

Financial Implications

Damages awarded (if any): Specific damages were not awarded, but the builder was required to rectify the identified defects.

How the Section 18F defence affected the damages: The rejection of the defence did not impact damages due to no financial penalties being specified, but it affirmed the builder’s responsibility to rectify defects.

Costs awarded: The builder must pay the homeowners’ costs of the appeal as part of the order.

Lessons for Homeowners

Key takeaways from the case: Homeowners should ensure clear communication and documentation regarding their building contracts and any professional engagements.

Potential pitfalls to avoid: Relying solely on builder-provided professionals without ensuring their independence can lead to complications in disputes.

Importance of documentation and professional advice: Maintaining thorough documentation and ensuring the involvement of independent professionals can help protect homeowners’ interests.

Broader Implications

Impact on similar cases: This case serves as a warning for builders and homeowners alike to clearly define responsibilities in construction contracts.

Potential changes to industry practices: There may be a push for tighter regulations around builders’ responsibilities and the hiring of design professionals.

Any suggested legislative or regulatory changes: Recommendations may include stricter oversight in building designs and clearer guidelines around compliance with design specifications.

Take Warranty
Wisdom into Action

Use HBApp to apply legal insights 
to your home project

Need Expert Advice on Your Building Dispute?

While our case summaries provide valuable insights, every building dispute is unique.

Get personalised guidance from a qualified professional.

Begin Your Journey to a Dream Home Today

Ready to transform your home building experience? Sign up for a free trial and unlock the full potential of Home Building App. Discover how our comprehensive project management tools can simplify your build, ensuring your project remains on time, within budget, and of the highest quality.