Singh v Zamaneh

Table of Contents

Case Overview

The case of Singh v Zamaneh (2023) NSWCATAP 248 pertains to a residential building dispute in New South Wales. The decision was handed down by the Civil and Administrative Tribunal on 30 August 2023, following a hearing held on 02 May 2023. The appeal was presided over by S Thode, Principal Member, and J S Currie, Senior Member.

Project Details

This case revolved around roofing work carried out at a property in Moorebank, owned by the appellant, Jai Singh. The original contract price for the project was $37,000, with a disputed outstanding balance of $2,200.

Parties Involved

The key parties in this dispute include:

  • Homeowner: Jai Singh (Self-represented)
  • Builder: Vahid (Victor) Zamaneh (Self-represented)

Nature of the Dispute

The conflict centred around roofing work that was to be completed by the builder. The homeowner asserted that:

  • The builder performed unlicensed and uninsured work under a contract that did not comply with the Home Building Act.
  • Specific statutory warranties under Section 18B of the Home Building Act were not fulfilled.

Critical to this case was the homeowner’s claim for reimbursement of $4,540 for asserted losses and damages resulting from the builder’s failures.

Claim Details

Jai Singh sought the following remedies from the Tribunal:

  • Refund of all moneys paid to the builder.

Key Findings

The Tribunal’s determinations included:

  • No breach of Section 18B was established due to insufficient evidence and the builder’s unlicensed status.
  • The tribunal member highlighted that the homeowner’s evidence (consisting of emails, photos, and notes) did not satisfactorily demonstrate the builder’s breach of contract or statutory warranties.
  • Despite the homeowner’s assertions regarding the builder’s breaches, the lack of supporting expert evidence undermined his claims.

Outcome

In the final determination, the Tribunal ruled in favour of the builder. The key outcomes were:

  • Leave to appeal was refused.
  • The appeal was dismissed on the grounds that the evidence did not support claims of procedural unfairness or misapplication of the law.
  • Consequently, the appellant was not entitled to any financial recovery from the builder, and it was declared that $2,200 was not owing.

Key Sections and Interpretation of the Home Building Act and Relevant Case Precedents

The court’s interpretation of Section 18B was pivotal in this case. It principally addresses the warranties that builders are required to adhere to under the Home Building Act, including:

  • Compliance with licensing requirements.
  • Provision of quality workmanship and materials.

Take Warranty
Wisdom into Action

Use HBApp to apply legal insights 
to your home project

Need Expert Advice on Your Building Dispute?

While our case summaries provide valuable insights, every building dispute is unique.