The Sydney Building Company Limited v Sinac

Table of Contents

Case Overview

Case name and citation: The Sydney Building Company Limited v Sinac (2019 NSWCATAP 43)

Date of decision: 15 February 2019

Tribunal/court name: Civil and Administrative Tribunal, New South Wales

Parties Involved

Homeowner details: Lorna Sinac (respondent)

Builder details: The Sydney Building Company Limited (appellant)

Nature of the Dispute

This case revolved around significant issues of jurisdiction and timing of claims under the Home Building Act 1989. The homeowner alleged breaches of statutory warranties due to defective work. Specific defects included:

  • Defective works
  • Water ingress

Claim Details

Amount claimed by the homeowner: $186,611.85

Specific remedies sought: Payment for defective works

Key Findings

The tribunal found that the Sydney Building Company had indeed breached the statutory warranties under the Home Building Act. The determination centred on:

  • Classification of defects as significant, causing water ingress
  • The builder was deemed responsible for the identified defects

Outcome

The tribunal’s decision favoured the homeowner, ordering the builder to pay damages amounting to $186,611.85. There were no financial benefits awarded apart from the damages.

Key Sections and Interpretation of the Home Building Act and Relevant Case Precedents

This case reaffirmed the application of Section 18B of the Home Building Act, which concerns the statutory warranties that builders must adhere to.

Take Warranty
Wisdom into Action

Use HBApp to apply legal insights 
to your home project

Need Expert Advice on Your Building Dispute?

While our case summaries provide valuable insights, every building dispute is unique.

Get personalised guidance from a qualified professional.

Begin Your Journey to a Dream Home Today

Ready to transform your home building experience? Sign up for a free trial and unlock the full potential of Home Building App. Discover how our comprehensive project management tools can simplify your build, ensuring your project remains on time, within budget, and of the highest quality.