Touma v Colantuono

Table of Contents

Case Overview

The case of Touma v Colantuono, cited as [2021] NSWCATAP 152, was decided by the Civil and Administrative Tribunal of New South Wales on 26 May 2021. This matter was brought before the Tribunal’s Appeal Panel, composed of Principal Member K. Rosser and Senior Member M. Gracie.

Project Details

This dispute arose from a residential building project involving a contract for carpentry and other construction works valued at $26,500. The work began in March 2020.

Parties Involved

The parties involved in this case were:

  • Homeowner: Anthony Colantuono, representing himself.
  • Builder: Salim Touma trading as ST Carpentry & Constructions, represented by Sydney Metropolitan Lawyers.
  • Additional Party: ST Carpentry & Constructions Pty Ltd (the company) was also named as a second appellant in the proceedings.

Nature of the Dispute

The dispute primarily stemmed from allegations of defective and incomplete work, which the homeowner claimed violated the Section 18B warranties under the Home Building Act. The specific issues included:

  • Defective work involving various installations that were not completed to the expected standards.
  • Incomplete work, including a pergola and eaves that remained uninstalled.

Claim Details

Mr. Colantuono filed a claim on 23 June 2020, seeking rectification of defects and completion of unfinished work. In a counter-claim, Mr. Touma asserted he was owed $8,000 for unpaid work performed.

Key Findings

The Tribunal’s determination indicated that:

  • There was a contract for residential building work, but it was not compliant with Section 7 of the Home Building Act, as Mr. Touma failed to obtain the required Home Building Compensation Fund (HBCF) insurance.
  • The Tribunal found that considerable defects existed in the work performed, and as a result, Mr. Touma was not licensed to conduct the type of work undertaken.
  • Mr. Colantuono had paid a total of $19,500 for work which ultimately fell short of contractual expectations.

Outcome

The Tribunal ruled in favour of Mr. Colantuono, ordering Mr. Touma to pay him a total of $28,000 for the outstanding works and rectifications as identified in the expert report provided by a building professional. Furthermore, the appeal lodged by Mr. Touma was dismissed.

Important Considerations

The Tribunal highlighted several crucial aspects of this case:

  • The reliance on expert evidence played a significant role, as the work was assessed to be below acceptable standards, leading to the determination of defects.
  • The case illustrated a need for builders to understand their obligations under the Home Building Act, particularly concerning licensing and insurance.

Key Sections and Interpretation of the Home Building Act and Relevant Case Precedents

The decision invoked various legal principles under Section 18B, primarily focusing on warranties for quality and completion of building work. It reiterated the importance of compliance with the Home Building Act.

Take Warranty
Wisdom into Action

Use HBApp to apply legal insights 
to your home project

Need Expert Advice on Your Building Dispute?

While our case summaries provide valuable insights, every building dispute is unique.